Dedicated GPU clusters
HGX B300 clusters of 64, 128 or 288 nodes, built to our published delivery specification, burned in before handover and run on a fabric no other customer uses.
A 1Legion GPU cluster is a complete NVIDIA HGX B300 system dedicated to one customer: GPU servers, CPU nodes, control plane, storage, a non-blocking east-west fabric, the north-south network and the internet edge. We build it to our published delivery specification, burn it in with NVIDIA's hardware validation tests, and operate it for the full 36 to 60 month term.
What a dedicated AI cluster includes
Every layer of the cluster serves one customer, from the GPUs to the north-south network, and every layer is specified in writing before you sign.
| Node | Role | Specification |
|---|---|---|
| GPU node | Runs your training and inference | NVIDIA HGX B300, 8 GPUs with 270 GB of HBM3e each; at least 128 vCPUs; 3 TB of system memory preferred, at least 1.92 TB; at least 9.2 TB of raw local NVMe; 800 Gb/s per GPU on NVIDIA ConnectX-8 (preferred); NVIDIA BlueField-3 frontend at 2 x 400 Gb/s (preferred); air cooled on the OEM's recommendation |
| CPU node | Runs the services around the GPUs: serving, routing and batch | x86, at least 128 vCPUs at a base clock above 3 GHz, AMD EPYC 9565 or 9575F preferred; 4 GB of memory per thread; BlueField-3 frontend |
| Control plane node | The cluster's control plane | 32 vCPUs above 3.65 GHz, AMD EPYC 9175F preferred; 128 GB of memory; six nodes per 2,304 GPUs, spread over two racks |
CPU nodes are sized from the GPU count: at least 6 hardware threads and 24 GB of memory for every GPU in the cluster. B300 for AI model labs describes what sustained training asks of each layer.
HGX B300 cluster reference configurations
Three reference sizes fix how many CPU nodes, control plane nodes, storage and megawatts go with a given number of GPU nodes.
| Item | 64 nodes | 128 nodes | 288 nodes |
|---|---|---|---|
| GPU nodes (8 GPUs each) | 64 | 128 | 288 |
| GPUs | 512 | 1,024 | 2,304 |
| CPU nodes | 24 | 48 | 108 |
| Control plane nodes | 6 | 6 | 6 |
| Storage, appliance option (usable) | 512 TB | 1,024 TB | 2,304 TB |
| Storage, storage-node option | 9 nodes | 17 nodes | 38 nodes |
| Estimated IT load | about 0.98 MW | about 1.95 MW | about 4.39 MW |
The ratios hold at every size. With 24, 48 and 108 CPU nodes of 128 vCPUs, each GPU gets 6 hardware threads. The storage appliance holds at least 1 TB usable per GPU. Six control plane nodes cover all three sizes, because the specification sets six per 2,304 GPUs. In total, the three sizes hold about 138 TB, 276 TB and 622 TB of HBM3e, and they fit within 1 MW, 2 MW and 4.4 MW of IT load.
Larger by design
The reference sizes stop at 288 nodes; the design does not. The specification sizes each layer per GPU: 800 Gb/s of fabric, 6 CPU threads and 24 GB of CPU memory, and 1 TB of usable storage. A larger cluster keeps those ratios, and your proposal sets out the design, the site and the power. HGX B300 clusters run in Toronto today, and capacity in Delaware, in the United States, is coming online.
The east-west fabric: Ethernet or InfiniBand
Every GPU has its own 800 Gb/s into a rail-optimized, fully non-blocking fabric that carries only your traffic.
- Bandwidth: 1 x 800 Gb/s or 2 x 400 Gb/s planes per GPU, 6.4 Tb/s per server, with NVIDIA ConnectX-8 NICs preferred.
- Rail optimized: the NIC of GPU 1 in every server connects to rail 1, GPU 2 to rail 2, and so on.
- Non-blocking: no oversubscription in the fabric, so every GPU can send at full rate at the same time.
- Switching: NVIDIA Spectrum-X or Broadcom Tomahawk 6 preferred; NVIDIA Quantum InfiniBand or Tomahawk 5 accepted.
- Tested before handover: NCCL throughput with nccl-tests, with SHARP where supported (HW-1), and every InfiniBand or RoCE rail with ib_write_bw (HW-2).
Foundation model training bottlenecks explains why interconnect and memory bandwidth, more than GPU count, set training throughput.
Storage, north-south and the edge
Storage and the networks around the fabric are specified per GPU and per node, in the same document as the GPUs.
- Storage, option A: a vendor-managed appliance from VAST Data, WEKA or DDN, at least 1 TB usable per GPU, with 24/7 vendor escalation and committed throughput and latency per tier.
- Storage, option B: storage nodes for your own storage software, at least 3 TB raw per GPU on 30.72 TB NVMe PCIe 5.0 drives, minimum 9 nodes.
- North-south: 400 Gb/s per node preferred, 200 Gb/s minimum; no oversubscription on storage leaves and below 4:1 on GPU leaves; RoCEv2 and MTU 9000.
- Edge: two independent transit providers at 100 Gb/s per circuit, eBGP with BFD, and DDoS scrubbing activated through BGP within 5 minutes.
NAT, public addresses, your own IP space and ASN, and flow telemetry are covered on storage and networking.
Power planning for a GPU cluster
Plan on about 14 kW per GPU node: with CPU nodes, control plane, storage nodes and network added, a 64-node cluster needs about 0.98 MW of IT load.
| 64-node cluster | Count | Planning figure | Load |
|---|---|---|---|
| GPU nodes | 64 | about 14 kW each | 896 kW |
| CPU nodes | 24 | 1.0 kW each | 24 kW |
| Control plane nodes | 6 | 0.5 kW each | 3 kW |
| Storage nodes, option B | 9 | 1.3 kW each | 11.7 kW |
| Network | 5 percent of GPU load | 44.8 kW | |
| Total | about 0.98 MW |
The same method gives about 1.95 MW for 128 nodes and 4.39 MW for 288. The 14 kW figure is a working assumption for an air-cooled HGX B300 node; NVIDIA lists about 14 kW for its own DGX B300 system. The facility must commit to a contractual maximum kW per rack, and that number decides how many GPU nodes share a rack. Data centers lists what else we require of a site.
How a cluster is delivered
A cluster moves from proposal to production in five steps, and the acceptance report marks the line between building it and running it.
Proposal
We send a written proposal against the delivery specification. Every item is marked Required or Preferred, and any change you need is listed as a numbered deviation.
Contract and onboarding
The company that will run the cluster completes three onboarding forms, signs the rental agreement and pays the down payment. Larger allocations may need a bank guarantee or letter of credit.
Build
We rack the servers, build the fabric, the north-south network and the edge, and record every rack, node, GPU, NIC, drive, switch, port, transceiver and cable in an authoritative inventory.
Burn-in
The cluster passes NVIDIA's hardware validation tests HW-1 to HW-5: NCCL throughput, every fabric rail, GPUDirect RDMA and storage, NVLink and NVSwitch, and a 24-hour soak at a sustained power cap.
Handover and operations
You receive the acceptance report with every result. We then run the cluster under our operating commitments, with a shared Slack channel and a named technical account owner.
Burn-in and acceptance describes each test and what happens when a node fails one.
Questions buyers ask
Is the fabric InfiniBand or Ethernet?
Our delivery specification prefers Ethernet on NVIDIA Spectrum-X or Broadcom Tomahawk 6, and accepts NVIDIA Quantum InfiniBand or Tomahawk 5. Either way, the fabric is rail optimized, fully non-blocking and 800 Gb/s per GPU.
Is the cluster shared with other customers?
No. The GPU servers, the east-west fabric and the north-south network are dedicated to one customer.
How much power does a GPU cluster need?
About 0.98 MW of IT load for 64 nodes, 1.95 MW for 128 and 4.39 MW for 288, planned at about 14 kW per GPU node.
Are the GPU nodes air or liquid cooled?
HGX B300 nodes are air cooled, on the OEM's recommendation at cluster scale. GB300 NVL72, available by reservation, is liquid cooled.
Do we see the burn-in results?
Yes. Every cluster passes NVIDIA's hardware validation tests HW-1 to HW-5 before handover, and the results come to you in an acceptance report. See burn-in and acceptance.
Can a cluster be larger than 288 nodes?
Yes. The specification sizes every layer per GPU, so a larger cluster keeps the same ratios. Your proposal sets out the design, the site and the power.
Tell us what you need to run.
Share the hardware, the number of servers, the term and the start date. You receive a written proposal built on our delivery specification.